STEEL CONSTRUCTION FASTENERS

10

1.5

Observations on the use of HV sets

• HV bolt assemblies should only contain bolts, nuts and washers from one manufacturer.

• Protect all products against dirt during storage and delivery.

• HV washers should be installed with the chamfered edge facing outwards from the structure.

• HV nuts should be with labelling facing outwards for any post-installation inspection.

• The assembly must always be tightened by rotating the nut.

• Do not lubricate the bolt or nut before tightening! Values indicated by the manufacturer only apply to products in

as-delivered state.

• Tightening inspections are subject to the requirements of EN ISO 1090-2.

• If a preloaded assembly is opened at a later stage, it must be replaced with a new assembly. Re-preloading of the